§ 23.5-5. Contractor's duties generally.  


Latest version.
  • The contractor, as defined in section 23.5-2, shall within the corporate limits of the city, collect and dispose of all solid waste collected and placed at the curb by residential customers in accordance with this chapter, all in the manner provided for by written agreement between the contractor and the city, and by applicable law. Collection by the contractor shall be twice per week for all residential customers in the city. There shall be at least two (2) days intervening between the first collection of each week and the second collection per week. No collection shall transpire on New Year's Day, Memorial Day, July 4th, Labor Day, Thanksgiving and Christmas Day, and the weeks in which those holidays fall shall be exceptions to the requirement for twice weekly collection.

(Ord. of 12-19-95)